RRB Junior Engineer / DMS / CMA 2019 · Question 17 of 3719
Mathematics - Time and Work
Let, total work = (LCM of 11, 20, and 55) = 220 efficiency of P = 20 units Efficiency of Q = 11 units Efficiency of R = 4 units Work done by P and Q in first day = 20 + 11 = 31 Work done by P and R in second day = 20 + 4 = 24 Total work done by P, Q, and R in 2 days = 31 + 24 = 55 55-unit work done by all three in = 2 days 220-unit work done by all thee in = [2/55] × 220 = 8 days.
Source: RRB JE 2019 CBT-1 (24-May-2019 Shift-2) — ixambee compilation with answer key and solutions · reliable-secondary