Testwala logoTestwala
HomeMocksPracticePYQsDashboard
Testwala logoTestwala

Timing-accurate mock tests and PYQs for SSC, Banking and Railway exams — so the real paper feels like a revision.

Exams

  • SSC exams
  • Banking exams
  • Railway exams
  • All exams

Practice

  • Practice questions
  • Mock test series
  • Sectional tests
  • Year-wise PYQs
  • Performance analytics

Company

  • About us
  • Help Centre
  • Pricing
  • Sign in

Legal

  • Privacy Policy
  • Terms of Service

Contact

  • hello@testwala.co.in
  • Telegram
  • +91 62816 87760

Practice interface modeled on the official exam pattern — not the official examination. Testwala is not affiliated with the Staff Selection Commission, IBPS, SBI, RBI, NABARD, SEBI or Indian Railways.

© 2026 Testwala. All rights reserved.

Built for aspirants, by aspirants.

HomeMocksPracticeStats
  1. Home
  2. ›
  3. PYQs
  4. ›
  5. ibps-so
  6. ›
  7. 2016
  8. ›
  9. Q32

ibps-so 2016 · Question 32 of 394

Two distinct exercises were carried out upon the cheque-return module of Chandrabhaga Urban Bank. In the rst, the design documents and the code were reviewed against the approved speci cation, and every requirement in that speci cation was traced to the design element and the module that implemented it, so as to establish that what had been built agreed with what had been speci ed. In the second, the nished module was placed before the o cers of three branches and exercised upon a fortnight of real return memos, so as to establish that what had been speci ed was in fact what the branches needed to do their work. The two exercises are, respectively:

  1. AVeri cation and validation — veri cation asking whether the product is being built right, that is, in conformity with its speci cation, and validation asking whether the right product is being built, that is, one that meets the user's actual needCorrect
  2. BValidation and veri cation — validation asking whether the product conforms to its speci cation and veri cation whether it meets the user's need
  3. CUnit testing and integration testing — the rst exercising a module in isolation and the second the assembled modules together
  4. DQuality control and quality assurance — the rst improving the process by which the product is made and the second examining the product itself by users at their own premises
  5. EAlpha testing and beta testing — the rst conducted by the developer's own sta and the second

Answer: A. Veri cation and validation — veri cation asking whether the product is being built right, that is, in conformity with its speci cation, and validation asking whether the right product is being built,…

Official answer key verified. Detailed explanation coming soon.

Source: IBPS SO 2016 IT Officer (held 28-29 Jan 2017, single-stage CWE) - Prepp · memory-based