TNPSC Group-I 2025 · Question 27 of 66
Aptitude - Time and Work
Let Q work x days; P works (x+8) days. x/40 + (x+8)/20 = 1 gives 3x/40 = 0.6, so x = 8 days.
Source: TNPSC Group-I Prelims 2025 (held 15 June 2025) - official question paper via tnpscinfo.com (Impacteers TNPSC Coaching compilation)