Telangana Police SI 2018 · Question 1 of 96
Time and Work
A does 1/12 of the work per day and B does 1/16 per day. Together they do 1/12 + 1/16 = 7/48 per day. In 4 days they complete 4 x 7/48 = 7/12 of the work. Remaining work = 1 - 7/12 = 5/12. A alone needs (5/12) / (1/12) = 5 days.
Source: TSLPRB SCT SI Civil PWT 2018 official paper (Arithmetic & Test of Reasoning); answer verified by worked solution