SSC MTS & Havaldar 2016 · Question 130 of 162
⇒ A’s 1 day work = 1 / 20 ⇒ A worked for 5 days ⇒ Then, A’ 5 days’ work = (1 / 20) ⨯ 5 = 1 / 4 ⇒ Remaining work = 1 - 1 / 4 = 3 / 4 ⇒ Now, B finished 3/4 of the work in 42 days ∴ Whole work done by B alone = 42 ⨯ 4 / 3 = 56 days