Testwala logoTestwala
HomeMocksPracticePYQsDashboard
Testwala logoTestwala

Timing-accurate mock tests and PYQs for SSC, Banking and Railway exams — so the real paper feels like a revision.

Exams

  • SSC exams
  • Banking exams
  • Railway exams
  • All exams

Practice

  • Practice questions
  • Mock test series
  • Sectional tests
  • Year-wise PYQs
  • Performance analytics

Company

  • About us
  • Help Centre
  • Pricing
  • Sign in

Legal

  • Privacy Policy
  • Terms of Service

Contact

  • hello@testwala.co.in
  • Telegram
  • +91 62816 87760

Practice interface modeled on the official exam pattern — not the official examination. Testwala is not affiliated with the Staff Selection Commission, IBPS, SBI, RBI, NABARD, SEBI or Indian Railways.

© 2026 Testwala. All rights reserved.

Built for aspirants, by aspirants.

HomeMocksPracticeStats
  1. Home
  2. ›
  3. PYQs
  4. ›
  5. SSC MTS & Havaldar
  6. ›
  7. 2014
  8. ›
  9. Q54

SSC MTS & Havaldar 2014 · Question 54 of 82

Raju can do a piece of work in 20 days, while Ram can do it in 30 days. If both of them work at it. together, then the number of days in which they will be able to finish the work is

  1. A12 daysCorrect
  2. B10 days
  3. C50 days
  4. D25 days

Answer: A. 12 days

Explanation

Let total work is L.C.M. (20,30) = 60 units 60 Raju alone can complete the work in 20 days, => Raju's efficiency = 20 = 3 units/day 60 Similarly Ram's efficiency = 30 = 2 units/day Now, (Raju+Ram)'s 1 day's work = 3 + 2 = 5 units/day 60 ∴ Days required by Raju and Ram together to complete the work = 5 = 12 days

Source: Solved SSC MTS 23 February 2014 Shift 1 Paper with Solutions · reliable-secondary

← Q53View full paper (82 questions)Q55 →