PYQPulse
HomeMocksPracticePYQsUpdatesDashboard
PYQPulse

Timing-accurate mock tests and PYQs for SSC, Banking and Railway exams — so the real paper feels like a revision.

Exams

  • SSC exams
  • Banking exams
  • Railway exams
  • All exams

Practice

  • Practice questions
  • Mock test series
  • Sectional tests
  • Year-wise PYQs
  • Performance analytics

Company

  • About us
  • Help Centre
  • Pricing
  • Sign in

Legal

  • Privacy Policy
  • Terms of Service

Contact

  • hello@testwala.co.in
  • Telegram
  • +91 62816 87760

Practice interface modeled on the official exam pattern — not the official examination. PYQPulse is not affiliated with the Staff Selection Commission, IBPS, SBI, RBI, NABARD, SEBI or Indian Railways.

© 2026 PYQPulse. All rights reserved.

Built for aspirants, by aspirants.

HomeMocksPracticeStats
  1. Home
  2. ›
  3. PYQs
  4. ›
  5. SSC GD Constable
  6. ›
  7. 2015
  8. ›
  9. Q33

SSC GD Constable 2015 · Question 33 of 88

8 children and 12 men complete a certain piece of work in 9 days, Each child takes twice the time taken by a man to finish the work. In how many days will 12 men finish the same work ?

  1. A9 days
  2. B13 days
  3. C12 daysCorrect
  4. D15 days

Answer: C. 12 days

Explanation

Each child takes twice the time taken by a man to finish the work, => 2 children = 1 man Thus, 8 children = 4 men Hence, (4+12) = 16 men complete the work in 9 days. => 12 men will finish in = => Ans - (C) 16×9 12 = 12 days

Source: Solved SSC GD 2015 Paper with Solutions — Collegedunia · reliable-secondary

← Q32View full paper (88 questions)Q34 →

Practice the full SSC GD Constable 2015 paper

Timed test with all 88 questions, just like the real exam.

Start test