PYQPulse
HomeMocksPracticePYQsUpdatesDashboard
PYQPulse

Timing-accurate mock tests and PYQs for SSC, Banking and Railway exams — so the real paper feels like a revision.

Exams

  • SSC exams
  • Banking exams
  • Railway exams
  • All exams

Practice

  • Practice questions
  • Mock test series
  • Sectional tests
  • Year-wise PYQs
  • Performance analytics

Company

  • About us
  • Help Centre
  • Pricing
  • Sign in

Legal

  • Privacy Policy
  • Terms of Service

Contact

  • hello@testwala.co.in
  • Telegram
  • +91 62816 87760

Practice interface modeled on the official exam pattern — not the official examination. PYQPulse is not affiliated with the Staff Selection Commission, IBPS, SBI, RBI, NABARD, SEBI or Indian Railways.

© 2026 PYQPulse. All rights reserved.

Built for aspirants, by aspirants.

HomeMocksPracticeStats
  1. Home
  2. ›
  3. PYQs
  4. ›
  5. SSC CPO (SI in Delhi Police & CAPFs)
  6. ›
  7. 2023
  8. ›
  9. Q109

SSC CPO (SI in Delhi Police & CAPFs) 2023 · Question 109 of 377

P, Q and R, when working individually, can complete a job in, respectively, 36 days, 48 days and 144 days. P, Q and R start working together. P leaves the job 12 days before completion and Q leaves the job 8 days before completion. R works from the beginning till the end of the job. Determine the total number of days taken to complete the job.

not-specified

  1. A24
  2. B27Correct
  3. C30
  4. D25

Answer: B. 27

Official answer key verified. Detailed explanation coming soon.

Source: SSC CPO 2023 Paper-I (03-Oct-2023 Shift 1) candidate response sheet (evidyarthi mirror) + SSC CPO 2023 Paper-I (03-Oct-2023 Shift 1) solved paper with answer key (oswaal360) · reliable-secondary