PYQPulse
HomeMocksPracticePYQsUpdatesDashboard
PYQPulse

Timing-accurate mock tests and PYQs for SSC, Banking and Railway exams — so the real paper feels like a revision.

Exams

  • SSC exams
  • Banking exams
  • Railway exams
  • All exams

Practice

  • Practice questions
  • Mock test series
  • Sectional tests
  • Year-wise PYQs
  • Performance analytics

Company

  • About us
  • Help Centre
  • Pricing
  • Sign in

Legal

  • Privacy Policy
  • Terms of Service

Contact

  • hello@testwala.co.in
  • Telegram
  • +91 62816 87760

Practice interface modeled on the official exam pattern — not the official examination. PYQPulse is not affiliated with the Staff Selection Commission, IBPS, SBI, RBI, NABARD, SEBI or Indian Railways.

© 2026 PYQPulse. All rights reserved.

Built for aspirants, by aspirants.

HomeMocksPracticeStats
  1. Home
  2. ›
  3. PYQs
  4. ›
  5. SSC CPO (SI in Delhi Police & CAPFs)
  6. ›
  7. 2018
  8. ›
  9. Q124

SSC CPO (SI in Delhi Police & CAPFs) 2018 · Question 124 of 195

A and B can finish a work together in 3 2 3 days. C and D can finish the same work in 3 1 7 days. If A, B, C and D do the work together, how long will it take for them to finish half of the work?

  1. A1 1 13 daysCorrect
  2. B8 13 day
  3. C2 13 days
  4. D11 13 days

Answer: A. 1 1 13 days

Official answer key verified. Detailed explanation coming soon.

Source: SSC CPO 2018 Tier-I Previous Paper (15-Mar-2019 Shift 2) Part 3 — doorsteptutor/examrace · reliable-secondary

← Q123View full paper (195 questions)Q125 →