PYQPulse
HomeMocksPracticePYQsUpdatesDashboard
PYQPulse

Timing-accurate mock tests and PYQs for SSC, Banking and Railway exams — so the real paper feels like a revision.

Exams

  • SSC exams
  • Banking exams
  • Railway exams
  • All exams

Practice

  • Practice questions
  • Mock test series
  • Sectional tests
  • Year-wise PYQs
  • Performance analytics

Company

  • About us
  • Help Centre
  • Pricing
  • Sign in

Legal

  • Privacy Policy
  • Terms of Service

Contact

  • hello@testwala.co.in
  • Telegram
  • +91 62816 87760

Practice interface modeled on the official exam pattern — not the official examination. PYQPulse is not affiliated with the Staff Selection Commission, IBPS, SBI, RBI, NABARD, SEBI or Indian Railways.

© 2026 PYQPulse. All rights reserved.

Built for aspirants, by aspirants.

HomeMocksPracticeStats
  1. Home
  2. ›
  3. PYQs
  4. ›
  5. SSC CHSL
  6. ›
  7. 2025
  8. ›
  9. Q309

SSC CHSL 2025 · Question 309 of 333

A contractor estimated that a project would cost 75,00,000. He planned for 60% of the cost to go to materials, 25% to labor, and the rest as contingency. iiowever, due to delays, material cost increased by 12.5%, labor cost increased by 10%, and contingency remained unchanged. What is the new total cost?

General

  1. A%5,45,000
  2. B%5,60,000
  3. C5,52,000
  4. D%5,50,000Correct

Answer: D. %5,50,000

Official answer key verified. Detailed explanation coming soon.

Source: SSC CHSL 2025 Tier-I (30 Nov 2025, Shift 1) - response sheet via Oliveboard · reliable-secondary