SSC CHSL 2023 · Question 87 of 92
Time and Work
Given A and B can finish a work in 6 days and 4 days Formula used Work = time × efficiency Calculation A, alone worked for 2 days. Work done by A in 2 days = 2/6 = 1/3 Work done by A and B in 1 day = 1/6 + 1/4 = 5/12 Let the number of days worked by both be N. ⇒ 5/12 × N = 1 - 1/3 N = 8/5 Total time = 2 + 8/5 = 18/5 or 3(3/5) days The answer is 3(3/5) days.
Source: SSC CHSL 2023 (Tier-I) Previous Year Paper (07-Aug-2023) (Shift 2) — prepp.in solved paper · reliable-secondary