Testwala logoTestwala
HomeMocksPracticePYQsDashboard
Testwala logoTestwala

Timing-accurate mock tests and PYQs for SSC, Banking and Railway exams — so the real paper feels like a revision.

Exams

  • SSC exams
  • Banking exams
  • Railway exams
  • All exams

Practice

  • Practice questions
  • Mock test series
  • Sectional tests
  • Year-wise PYQs
  • Performance analytics

Company

  • About us
  • Help Centre
  • Pricing
  • Sign in

Legal

  • Privacy Policy
  • Terms of Service

Contact

  • hello@testwala.co.in
  • Telegram
  • +91 62816 87760

Practice interface modeled on the official exam pattern — not the official examination. Testwala is not affiliated with the Staff Selection Commission, IBPS, SBI, RBI, NABARD, SEBI or Indian Railways.

© 2026 Testwala. All rights reserved.

Built for aspirants, by aspirants.

HomeMocksPracticeStats
  1. Home
  2. ›
  3. PYQs
  4. ›
  5. SSC CHSL
  6. ›
  7. 2014
  8. ›
  9. Q128

SSC CHSL 2014 · Question 128 of 209

DIRECTIONS : In Question Nos. 96 to 100, a part of the sentence is A and B working separately can do a piece of work in 9 and 15 days respectively. If they work for a day alternately, with A beginning, then the work will completed in

  1. A10 days
  2. B11 daysCorrect
  3. C9 days
  4. D12 days

Answer: B. 11 days

Explanation

15 45 45 9 40 8 8 ´ = = 5 Ten days work = 45 45 9 8 1 - = 1 Remaining work = which is done by A on 9 9 11th day. Hence, the work will be completed in 11 days.

Source: SSC CHSL Solved Paper 16-11-2014 (Disha Publications) · reliable-secondary