PYQPulse
HomeMocksPracticePYQsDashboard
PYQPulse

Timing-accurate mock tests and PYQs for SSC, Banking and Railway exams — so the real paper feels like a revision.

Exams

  • SSC exams
  • Banking exams
  • Railway exams
  • All exams

Practice

  • Practice questions
  • Mock test series
  • Sectional tests
  • Year-wise PYQs
  • Performance analytics

Company

  • About us
  • Help Centre
  • Pricing
  • Sign in

Legal

  • Privacy Policy
  • Terms of Service

Contact

  • hello@testwala.co.in
  • Telegram
  • +91 62816 87760

Practice interface modeled on the official exam pattern — not the official examination. PYQPulse is not affiliated with the Staff Selection Commission, IBPS, SBI, RBI, NABARD, SEBI or Indian Railways.

© 2026 PYQPulse. All rights reserved.

Built for aspirants, by aspirants.

HomeMocksPracticeStats
  1. Home
  2. ›
  3. PYQs
  4. ›
  5. SSC CHSL
  6. ›
  7. 2012
  8. ›
  9. Q149

SSC CHSL 2012 · Question 149 of 202

A is thrice as good a workman as B and takes 60 days less than B for doing a job. The time in which they can do it together is:

  1. A15 days
  2. B30 days 1
  3. CdaysCorrect
  4. D60days 22 2

Answer: C. days

Explanation

If A can finish a work = x days B will do this work = 3x days From question, A – B = 3x – x = 60 Þ x = 30 A = 30 days, B = 90 days A’s 1 day work + B’s 1 day work = 1 1 4 + = 30 90 90 So, A and B working together can complete work = 90 4 = 22.5 days 10%­ 5%­ ¾¾¾® cost to B ¾¾¾® cost to C

Source: SSC CHSL Solved Paper 04-11-2012 (Disha Publications) · reliable-secondary

← Q148View full paper (202 questions)Q150 →

Practice the full SSC CHSL 2012 paper

Timed test with all 202 questions, just like the real exam.

Start test