SBI Junior Associate 2014 · Question 35 of 200
arithmetic
Time taken by A alone = 15 days Efficiency of A : B = 100 : 160 = 15 : 24 => Time taken by B = 24 days $$\therefore$$ (A + B)'s 1 day's work = $$\frac{1}{15} + \frac{1}{24}$$ = $$\frac{8 + 5}{120} = \frac{13}{120}$$ $$\therefore$$ Required time = $$\frac{1}{\frac{13}{120}}$$ = $$\frac{120}{13} = 9\frac{3}{13}$$ days
Source: SBI Clerk 27 July 2014 Paper with Solutions — Cracku · reliable-secondary