RRB NTPC 2026 · Question 73 of 93
Given: Time taken by Jitesh = 5 days Time taken by Kamal = 18 days Working together for 3 days Formula Used: 1 Work rate = Time Remaining Work Time = Individual Work Rate Solution: 1 Jitesh’s 1-day work = 5 1 Kamal’s 1-day work = 18 1 1 18 + 5 23 Combined 1-day work = + = = 5 18 90 90 23 23 Work done in 3 days = 3 × = 90 30 23 7 Remaining work = 1 − = 30 30 7 7 Time taken by Jitesh = 30 = 1 6 5 Final Answer: 7 days 6
Source: RRB NTPC CBT-I Memory-Based Paper 16 March 2026 S1 (careerpower test-platform compilation) · memory-based