PYQPulse
HomeMocksPracticePYQsUpdatesDashboard
PYQPulse

Timing-accurate mock tests and PYQs for SSC, Banking and Railway exams — so the real paper feels like a revision.

Exams

  • SSC exams
  • Banking exams
  • Railway exams
  • All exams

Practice

  • Practice questions
  • Mock test series
  • Sectional tests
  • Year-wise PYQs
  • Performance analytics

Company

  • About us
  • Help Centre
  • Pricing
  • Sign in

Legal

  • Privacy Policy
  • Terms of Service

Contact

  • hello@testwala.co.in
  • Telegram
  • +91 62816 87760

Practice interface modeled on the official exam pattern — not the official examination. PYQPulse is not affiliated with the Staff Selection Commission, IBPS, SBI, RBI, NABARD, SEBI or Indian Railways.

© 2026 PYQPulse. All rights reserved.

Built for aspirants, by aspirants.

HomeMocksPracticeStats
  1. Home
  2. ›
  3. PYQs
  4. ›
  5. RRB NTPC
  6. ›
  7. 2012
  8. ›
  9. Q62

RRB NTPC 2012 · Question 62 of 115

A and B can do a work in 18 and 24 days respectively. They worked together for 8 days and then A left. The remaining work was finished by B in

  1. A5 days
  2. B5 1 daysCorrect
  3. C8 days
  4. D10 days 3

Answer: B. 5 1 days

Official answer key verified. Detailed explanation coming soon.

Source: RRB NTPC Previous Year Paper-2012 (entri.app compilation, memory-based) · memory-based

← Q61View full paper (115 questions)Q63 →

Practice the full RRB NTPC 2012 paper

Timed test with all 115 questions, just like the real exam.

Start test