PYQPulse
HomeMocksPracticePYQsDashboard
PYQPulse

Timing-accurate mock tests and PYQs for SSC, Banking and Railway exams — so the real paper feels like a revision.

Exams

  • SSC exams
  • Banking exams
  • Railway exams
  • All exams

Practice

  • Practice questions
  • Mock test series
  • Sectional tests
  • Year-wise PYQs
  • Performance analytics

Company

  • About us
  • Help Centre
  • Pricing
  • Sign in

Legal

  • Privacy Policy
  • Terms of Service

Contact

  • hello@testwala.co.in
  • Telegram
  • +91 62816 87760

Practice interface modeled on the official exam pattern — not the official examination. PYQPulse is not affiliated with the Staff Selection Commission, IBPS, SBI, RBI, NABARD, SEBI or Indian Railways.

© 2026 PYQPulse. All rights reserved.

Built for aspirants, by aspirants.

HomeMocksPracticeStats
  1. Home
  2. ›
  3. PYQs
  4. ›
  5. RRB Junior Engineer / DMS / CMA
  6. ›
  7. 2019
  8. ›
  9. Q709

RRB Junior Engineer / DMS / CMA 2019 · Question 709 of 3719

If 200 men can dig a canal 8 hours a day in 6 days how long will take to dig a canal if 300 men work 6 hours a day

  1. A$$4\frac{2}{3}$$ days
  2. B6 days
  3. C7 days
  4. D$$5\frac{1}{3}$$ daysCorrect

Answer: D. $$5\frac{1}{3}$$ days

Official answer key verified. Detailed explanation coming soon.

Source: RRB JE 2019 CBT-1 (23-May-2019 Shift 1) — cracku.in solved paper with answer key · reliable-secondary