PYQPulse
HomeMocksPracticePYQsUpdatesDashboard
PYQPulse

Timing-accurate mock tests and PYQs for SSC, Banking and Railway exams — so the real paper feels like a revision.

Exams

  • SSC exams
  • Banking exams
  • Railway exams
  • All exams

Practice

  • Practice questions
  • Mock test series
  • Sectional tests
  • Year-wise PYQs
  • Performance analytics

Company

  • About us
  • Help Centre
  • Pricing
  • Sign in

Legal

  • Privacy Policy
  • Terms of Service

Contact

  • hello@testwala.co.in
  • Telegram
  • +91 62816 87760

Practice interface modeled on the official exam pattern — not the official examination. PYQPulse is not affiliated with the Staff Selection Commission, IBPS, SBI, RBI, NABARD, SEBI or Indian Railways.

© 2026 PYQPulse. All rights reserved.

Built for aspirants, by aspirants.

HomeMocksPracticeStats
  1. Home
  2. ›
  3. PYQs
  4. ›
  5. RRB Junior Engineer / DMS / CMA
  6. ›
  7. 2019
  8. ›
  9. Q157

RRB Junior Engineer / DMS / CMA 2019 · Question 157 of 3719

With P starting the work, working on alternate days, P and Q can finish a work in 17 days. If Q works on the first day and Q and P work alternately, the work is finished in 53/3 days. How many days will each take individually to execute the work?

Mathematics - Time and Work

  1. Aa. P = 35 days; Q = 35 days
  2. Bb. P = 35/3 days; Q = 35 daysCorrect
  3. Cc. P = 12 days; Q = 35 days
  4. Dd. P = 35 days; Q = 35/3 days

Answer: B. b. P = 35/3 days; Q = 35 days

Explanation

ˆLet P's 1 day work = x and Q's 1 day work = y If P start the work, working on alternate days, P and Q can finish a work in 17 days. P works for = 9 days Q works for = 8 days Total work = 9x + 8y If Q works on the first day and P and Q work alternately, the work is finished in 53/3 days =53/3 = 17+(2/3) Days Q works for = 9 days P work for = 8 + (2/3) = 26/3 days Total work = 9y + 26x/3 According to the question 9x + 8y = 9y + 26x/3 9x-26x/3 = 9y-8y x/3 = y x: y =3:1 Total work = 9x + 8y = 9×3+8×1 = 35 Q alone can finish the whole work in = 35/1 = 35 P alone can finish the whole work in = 35/3 days.

Source: RRB JE 2019 CBT-1 (24-May-2019 Shift-1) — ixambee compilation with answer key and solutions · reliable-secondary

← Q156View full paper (3719 questions)Q158 →

Practice the full RRB Junior Engineer / DMS / CMA 2019 paper

Timed test with all 3719 questions, just like the real exam.

Start test