RRB Junior Engineer / DMS / CMA 2015 · Question 14 of 480
Mathematics - Time and Work
1 day’s work of A = 1 day’s work of B = - 10 .-. 1 day’s work of A and p _ 1 1 _ 2 + 3 . 15 10 30 = 14s .-. A and B complete the work = -j - 6 days
Source: Arihant RRB JE Solved Paper 26-Aug-2015 (3rd Shift), Q91–150 — published solved-paper compilation (Q1–90 technical not included in this source) · memory-based