RRB Group D (Level-1 posts) 2022 · Question 358 of 598
Given: Time taken by pipe A to fill the tank = 21 hours Time taken by pipe B to fill the tank = 24 hours Formula used: Time = Total work⁄Efficiency Calculation: Here, extra 48 minutes represents the extra time taken by the pipes due to the leak. Total units of water to be filled = LCM of (21, 24) = 168 units. Pipe A can fill 8 units of water in 1 hr. Pipe B can fill 7 units of water in 1 hr. Normal Time is taken to fill the tank = 168⁄15 hrs = 11 3⁄15 hrs = 11 hrs 12 minutes. With 48 min extra, the pipes would take 12 hrs to fill the tank. Let the leakage can empty N units of water in 1 hr. (7 + 8 - N) × 12 = 168 15 - N = 14 N = 15 - 14 = 1 Leakage can empty 1 unit of water in 1 hr. Leakage of 168 units of water takes 168 hrs. Hence, the time taken to empty the tank is '168' hrs.
Source: RRB Group D 2022 Prev. Yr. Paper (18 Aug 2022) (Shift 2) - Prepp · reliable-secondary