PYQPulse
HomeMocksPracticePYQsUpdatesDashboard
PYQPulse

Timing-accurate mock tests and PYQs for SSC, Banking and Railway exams — so the real paper feels like a revision.

Exams

  • SSC exams
  • Banking exams
  • Railway exams
  • All exams

Practice

  • Practice questions
  • Mock test series
  • Sectional tests
  • Year-wise PYQs
  • Performance analytics

Company

  • About us
  • Help Centre
  • Pricing
  • Sign in

Legal

  • Privacy Policy
  • Terms of Service

Contact

  • hello@testwala.co.in
  • Telegram
  • +91 62816 87760

Practice interface modeled on the official exam pattern — not the official examination. PYQPulse is not affiliated with the Staff Selection Commission, IBPS, SBI, RBI, NABARD, SEBI or Indian Railways.

© 2026 PYQPulse. All rights reserved.

Built for aspirants, by aspirants.

HomeMocksPracticeStats
  1. Home
  2. ›
  3. PYQs
  4. ›
  5. MPSC State Service
  6. ›
  7. 2021 (CSAT)
  8. ›
  9. Q57

MPSC State Service 2021 · CSAT · Question 57 of 73

400 persons, working 9 hours a day complete 1/4 of the work in 10 days. How many additional persons, working 8 hours a day, required to complete the remaining work in 20 days?

Quantitative Aptitude

  1. A275Correct
  2. B250
  3. C675
  4. D400

Answer: A. 275

Explanation

Work = 400x9x10x4 units; remaining 3/4 needs 675 men at 8h/20d, so 275 additional: option (a).

Source: MPSC Rajyaseva Prelims 2021 – CSAT Paper II (Set D), official paper