PYQPulse
HomeMocksPracticePYQsUpdatesDashboard
PYQPulse

Timing-accurate mock tests and PYQs for SSC, Banking and Railway exams — so the real paper feels like a revision.

Exams

  • SSC exams
  • Banking exams
  • Railway exams
  • All exams

Practice

  • Practice questions
  • Mock test series
  • Sectional tests
  • Year-wise PYQs
  • Performance analytics

Company

  • About us
  • Help Centre
  • Pricing
  • Sign in

Legal

  • Privacy Policy
  • Terms of Service

Contact

  • hello@testwala.co.in
  • Telegram
  • +91 62816 87760

Practice interface modeled on the official exam pattern — not the official examination. PYQPulse is not affiliated with the Staff Selection Commission, IBPS, SBI, RBI, NABARD, SEBI or Indian Railways.

© 2026 PYQPulse. All rights reserved.

Built for aspirants, by aspirants.

HomeMocksPracticeStats
  1. Home
  2. ›
  3. PYQs
  4. ›
  5. APSC CCE
  6. ›
  7. 2024
  8. ›
  9. Q155

APSC CCE 2024 · Question 155 of 178

You are in charge of a time-bound infrastructure project in a remote place. During the project review meeting, you find that the project is likely to be delayed on account of lack of cooperation from the team members. In such a situation, you would

Decision Making

  1. Aask for replacement of team members
  2. Blook into the reasons for non-cooperation from the team members and try to mitigate themCorrect
  3. Cwarn the team members for their lack of cooperation
  4. Dask for extension of the project on some pretext

Answer: B. look into the reasons for non-cooperation from the team members and try to mitigate them

Explanation

The constructive response is to diagnose and address the reasons for non-cooperation; official key gives (B).

Source: APSC CCE Prelims 2024 GS Paper-II, official Series-A paper (DUCN-II-24/44-A), answer from official Series-A key

← Q154View full paper (178 questions)Q156 →

Practice the full APSC CCE 2024 paper

Timed test with all 178 questions, just like the real exam.

Start test